Heading to Henderson County High School this summer? We have some major campus improvements underway! Please check out the parking lot construction schedule below so you can plan ahead and avoid the roadblocks.
🗓️ Phase 1: Stadium Parking Lot
May 24–30: Equipment is moving onto the site.
June 1: Asphalt milling and paving operations officially begin.
⛔ CLOSURE: There will be NO ACCESS to the Stadium Lot via the Garden Mile entrance during this time.
🚗 Where to park: Please enter via Zion Road and park behind the Tech Unit.
⚽ Soccer Visitors: Please use the parking lot by the Tennis Courts.
🏁 Projected Completion: July 1
🗓️ Phase 2: Blue Unit Parking Lot
July 1: Asphalt milling and paving operations begin.
🏁 Projected Completion: Mid-July
🛑 Quick Tip: Please plan accordingly and allow yourself extra time for parking and traffic adjustments when visiting campus this summer.
Thank you so much for your patience, cooperation, and help in keeping everyone safe while we upgrade our facilities!